Regulations Designating Physical Activities
SCHEDULE(Sections 2 to 4)Physical Activities
Canadian Environmental Assessment Agency
1 The construction, operation, decommissioning and abandonment, in a wildlife area or migratory bird sanctuary, of
(a) an electrical generating station or transmission line;
(b) a dam, dyke, reservoir or other structure for the diversion of water;
(c) an oil or gas facility or oil and gas pipeline;
(d) a mine or mill;
(e) an industrial facility;
(f) a canal or lock;
(g) a marine terminal;
(h) a railway line or public highway;
(i) an aerodrome or runway; or
(j) a waste management facility.
2 The construction, operation, decommissioning and abandonment of
(a) a fossil fuel-fired electrical generating station with a production capacity of 200 MW or more; or
(b) a hydroelectric generating station with a production capacity of 200 MW or more.
3 The expansion of
(a) a fossil fuel-fired electrical generating station that would result in an increase in production capacity of 50% or more and 200 MW or more; or
(b) a hydroelectric generating station that would result in an increase in production capacity of 50% or more and 200 MW or more.
4 The construction, operation, decommissioning and abandonment of a tidal power electrical generating station with a production capacity of 5 MW or more, or an expansion of such a station that would result in an increase in production capacity of more than 35%.
5 The construction, operation, decommissioning and abandonment of an electrical transmission line with a voltage of 345 kV or more that is 75 km or more in length on a new right of way.
6 The construction, operation, decommissioning and abandonment of a dam or dyke that would result in the creation of a reservoir with a surface area that would exceed the annual mean surface area of a natural water body by 1 500 ha or more, or an expansion of a dam or dyke that would result in an increase in the surface area of a reservoir of more than 35%.
7 The construction, operation, decommissioning and abandonment of a structure for the diversion of 10 000 000 m3/a or more of water from a natural water body into another natural water body or an expansion of such a structure that would result in an increase in diversion capacity of more than 35%.
8 The construction, operation, decommissioning and abandonment of a facility for the extraction of 200 000 m3/a or more of ground water or an expansion of such a facility that would result in an increase in production capacity of more than 35%.
9 The construction, operation, decommissioning and abandonment of
(a) a heavy oil or oil sands processing facility with an oil production capacity of more than 10 000 m3/d; or
(b) an oil sands mine with a bitumen production capacity of more than 10 000 m3/d.
10 The construction, installation and operation of a facility for the production of oil or gas, if the facility is located offshore and
(a) is outside the limits of a study area delineated in
(i) an environmental assessment of a project for the offshore production of oil or gas that was conducted by a review panel or as a comprehensive study under the Canadian Environmental Assessment Act, or
(ii) an environmental assessment of a proposal for the offshore production of oil or gas that was conducted by a Panel under the Environmental Assessment Review Process Guidelines Order; or
(b) is inside the limits of a study area delineated in an environmental assessment described in subparagraph (a)(i) or (ii) and is not connected by an offshore oil and gas pipeline to a previously assessed facility in the study area.
11 The decommissioning and abandonment of a facility for the production of oil or gas if the facility is located offshore and it is proposed that the facility be disposed of or abandoned offshore or converted on site to another role.
12 The expansion of a heavy oil or oil sands processing facility that would result in an increase in oil production capacity that would exceed 5 000 m3/d and would raise the total oil production capacity to more than 10 000 m3/d.
13 The construction, decommissioning and abandonment, or an expansion that would result in an increase in production capacity of more than 35%, of
(a) an oil refinery, including a heavy oil upgrader, with an input capacity of more than 10 000 m3/d;
(b) a facility for the production of liquid petroleum products from coal with a production capacity of more than 2 000 m3/d;
(c) a sour gas processing facility with a sulphur inlet capacity of more than 2 000 t/d;
(d) a facility for the liquefaction, storage or regasification of liquefied natural gas, with a liquefied natural gas processing capacity of more than 3 000 t/d or a liquefied natural gas storage capacity of more than 50 000 t;
(e) a petroleum storage facility with a capacity of more than 500 000 m3; or
(f) a liquefied petroleum gas storage facility with a capacity of more than 100 000 m3.
14 The construction, operation, decommissioning and abandonment of
(a) an oil and gas pipeline more than 75 km in length on a new right of way; or
(b) an offshore oil and gas pipeline, if any portion of the pipeline is outside the limits of a study area delineated in
(i) an environmental assessment of a project for the offshore production of oil or gas that was conducted by a review panel or as a comprehensive study under the Canadian Environmental Assessment Act, or
(ii) an environmental assessment of a proposal for the offshore production of oil or gas that was conducted by a Panel under the Environmental Assessment Review Process Guidelines Order.
15 The construction, operation, decommissioning and abandonment of
(a) a metal mine, other than a gold mine, with an ore production capacity of 3 000 t/d or more;
(b) a metal mill with an ore input capacity of 4 000 t/d or more;
(c) a gold mine, other than a placer mine, with an ore production capacity of 600 t/d or more;
(d) a coal mine with a coal production capacity of 3 000 t/d or more; or
(e) a potash mine with a potassium chloride production capacity of 1 000 000 t/a or more.
16 The expansion of
(a) an existing metal mine, other than a gold mine, that would result in an increase in its ore production capacity of 50% or more, or 1 500 t/d or more, if the increase would raise the total ore production capacity to 3 000 t/d or more;
(b) an existing metal mill that would result in an increase in its ore input capacity of 50% or more, or 2 000 t/d or more, if the increase would raise the total ore input capacity to 4 000 t/d or more;
(c) an existing gold mine, other than a placer mine, that would result in an increase in its ore production capacity of 50% or more, or 300 t/d or more, if the increase would raise the total ore production capacity to 600 t/d or more;
(d) an existing coal mine that would result in an increase in its coal production capacity of 50 % or more, or 1 500 t/d or more, if the increase would raise the total coal production capacity to 3 000 t/d or more; or
(e) an existing potash mine that would result in an increase in its potassium chloride production capacity of 50% or more, or 500 000 t/a or more, if the increase would raise the total potassium chloride production capacity to 1 000 000 t/a or more.
17 The construction, operation, decommissioning and abandonment, or an expansion that would result in an increase in production capacity of more than 35%, of
(a) an asbestos mine;
(b) a salt mine with a brine production capacity of 4 000 t/d or more;
(c) an underground salt mine with a production capacity of 20 000 t/d or more;
(d) a graphite mine with a production capacity of 1 500 t/d or more;
(e) a gypsum mine with a production capacity of 4 000 t/d or more;
(f) a magnesite mine with a production capacity of 1 500 t/d or more;
(g) a limestone mine with a production capacity of 12 000 t/d or more;
(h) a clay mine with a production capacity of 20 000 t/d or more;
(i) a stone quarry or gravel or sand pit with a production capacity of 1 000 000 t/a or more; or
(j) a metal mine located offshore or on the ocean bed.
18 The construction, operation, decommissioning and abandonment of a pulp mill or pulp and paper mill.
19 The expansion of a pulp mill or pulp and paper mill that would result in an increase in its production capacity of more than 35% and more than 100 t/d.
20 The construction, operation, decommissioning and abandonment, or an expansion that would result in an increase in its production capacity of more than 35%, of
(a) a facility for the production of primary steel with a metal production capacity of 5 000 t/d or more;
(b) an industrial facility for the commercial production of non-ferrous metals or light metals by pyrometallurgy or high temperature electrometallurgy;
(c) a non-ferrous metal smelter located in the Yukon or Northwest Territories;
(d) a facility for the manufacture of chemical products with a production capacity of 250 000 t/a or more;
(e) a facility for the manufacture of pharmaceutical products with a production capacity of 200 t/a or more;
(f) a facility for the manufacture of wood products that are pressure-treated with chemical products, with a production capacity of 50 000 m3/a or more;
(g) a facility for the manufacture of plywood or particle board with a production capacity of 100 000 m3/a or more;
(h) a facility for the production of respirable natural mineral fibres;
(i) a leather tannery with a production capacity of 500 000 m2/a or more;
(j) a facility for the manufacture of primary textiles with a production capacity of 50 000 t/a or more;
(k) a factory for the manufacture of chemical explosives employing chemical processes; or
(l) a facility for the manufacture of lead-acid batteries.
21 The construction and operation outside an existing military base of a military base or station.
22 The construction, operation, decommissioning and abandonment outside an existing military base of a training area, range or test establishment for military training or weapons testing.
23 The expansion of a military base or station that would result in an increase in the area of the military base or station of more than 25%, or an increase in the cumulative floor area of existing buildings located on the military base or station of more than 25%.
24 The decommissioning and abandonment of a military base or station.
25 The testing of weapons for more than five days in a calendar year in an area other than those training areas, ranges and test establishments established under the authority of the Minister of National Defence for the testing of weapons prior to October 7, 1994.
26 The low-level flying of military fixed-wing jet aircraft for more than 150 days in a calendar year as part of a training program at an altitude below 330 m above ground level on a route or in an area that is not established by or under the authority of the Minister of National Defence or the Chief of the Defence Staff as a route or area set aside for low-level flying training prior to October 7, 1994.
27 The construction, operation, decommissioning and abandonment of
(a) a canal or any lock or associated structure to control water levels in the canal;
(b) a lock or associated structure to control water levels in existing navigable waterways; or
(c) a marine terminal designed to handle vessels larger than 25 000 DWT unless the terminal is located on lands that are routinely and have been historically used as a marine terminal or that are designated for such use in a land-use plan that has been the subject of public consultation.
28 The construction, operation, decommissioning and abandonment of
(a) a railway line more than 32 km in length on a new right of way;
(b) an all-season public highway that will be more than 50 km in length and either will be located on a new right-of-way or will lead to a community that lacks all-season public highway access; or
(c) a railway line designed for trains that have an average speed of more than 200 km/h.
29 The construction, operation, decommissioning and abandonment of
(a) an aerodrome located within the built-up area of a city or town;
(b) an airport; or
(c) an all-season runway with a length of 1 500 m or more.
30 The extension of an all-season runway by 1 500 m or more.
31 The construction, operation, decommissioning and abandonment of a facility used exclusively for the treatment, incineration, disposal or recycling of hazardous waste, or an expansion of such a facility that would result in an increase in its production capacity of more than 35%.
Canadian Nuclear Safety Commission
32 The construction, operation, decommissioning and abandonment, or an expansion that would result in an increase in production capacity of more than 35%, of
(a) a uranium mine, uranium mill or waste management system any of which is on a site that is not within the boundaries of an existing licensed uranium mine or uranium mill;
(b) a uranium mine, uranium mill or waste management system any of which is on a site that is within the boundaries of an existing licensed uranium mine or uranium mill, if the activity involves processes for milling or uranium tailings management that are not authorized under the existing licence;
(c) a Class IB nuclear facility for the refining or conversion of uranium that has a uranium production capacity of more than 100 t/a;
(d) a Class IA nuclear facility that is a nuclear fission reactor that has a production capacity of more than 25 MW(thermal);
(e) a Class IB nuclear facility that is a plant for the production of deuterium or deuterium compounds using hydrogen sulphide that has a production capacity of more than 10 t/a;
(f) a Class IB nuclear facility for the processing of irradiated nuclear fuel with an irradiated nuclear fuel input capacity of more than 100 t/a; or
(g) a Class IB nuclear facility that is on a site that is not within the boundaries of an existing licensed nuclear facility and that is for
(i) the storage of irradiated nuclear fuel, if the facility has an irradiated nuclear fuel inventory capacity of more than 500 t,
(ii) the processing or storage of radioactive waste other than irradiated nuclear fuel where
(A) the activity of the throughput of radioactive material with a half-life greater than one year is more than 1 PBq/a (1015 Bq/a), or
(B) the activity of the inventory of radioactive material with a half-life greater than one year is more than 1 PBq (1015), or
(iii) the disposal of radioactive nuclear substances.
33 The construction, operation, decommissioning and abandonment, in a wildlife area or migratory bird sanctuary, of
(a) a mine or mill;
(b) a nuclear facility; or
(c) a waste management facility.
National Energy Board
34 The construction, operation, decommissioning and abandonment of an electrical transmission line with a voltage of 345 kV or more that is 75 km or more in length on a new right of way.
35 The construction, operation, and installation of a facility for the production of oil or gas, if the facility is located offshore and
(a) is outside the limits of a study area delineated in
(i) an environmental assessment of a project for the offshore production of oil or gas that was conducted by a review panel or as a comprehensive study under the Canadian Environmental Assessment Act, or
(ii) an environmental assessment of a proposal for the offshore production of oil or gas that was conducted by a Panel under the Environmental Assessment Review Process Guidelines Order; or
(b) is inside the limits of a study area delineated in an environmental assessment described in subparagraph (a)(i) or (ii) and is not connected by an offshore oil and gas pipeline to a previously assessed facility in the study area.
36 The decommissioning and abandonment of a facility for the production of oil or gas if the facility is located offshore and it is proposed that the facility be disposed of or abandoned offshore or converted on site to another role.
37 The construction, operation, decommissioning and abandonment, or an expansion that would result in an increase in production capacity of more than 35%, of
(a) a sour gas processing facility with a sulphur inlet capacity of more than 2 000 t/d; or
(b) a petroleum storage facility with a capacity of more than 500 000 m3.
38 The construction, operation, decommissioning and abandonment of
(a) an oil and gas pipeline more than 75 km in length on a new right of way; or
(b) an offshore oil and gas pipeline, if any portion of the pipeline is outside the limits of a study area delineated in
(i) an environmental assessment of a project for the offshore production of oil or gas that was conducted by a review panel or as a comprehensive study under the Canadian Environmental Assessment Act, or
(ii) an environmental assessment of a proposal for the offshore production of oil or gas that was conducted by a Panel under the Environmental Assessment Review Process Guidelines Order.
39 The construction, operation, decommissioning and abandonment, in a wildlife area or migratory bird sanctuary, of
(a) an electrical transmission line; or
(b) an oil or gas facility or an oil and gas pipeline.
- Date modified: