Canada Oil and Gas Drilling and Production Regulations (SOR/2009-315)

Regulations are current to 2024-03-06 and last amended on 2009-12-31. Previous Versions

Canada Oil and Gas Drilling and Production Regulations

SOR/2009-315

CANADA OIL AND GAS OPERATIONS ACT

Registration 2009-11-26

Canada Oil and Gas Drilling and Production Regulations

P.C. 2009-1890 2009-11-26

Whereas, pursuant to subsection 15(1) of the Canada Oil and Gas Operations ActFootnote a, a copy of the proposed Canada Oil and Gas Drilling and Production Regulations, substantially in the annexed form, was published in the Canada Gazette, Part I on April 18, 2009 and interested persons were given an opportunity to make representations to the Minister of Natural Resources and the Minister of Indian Affairs and Northern Development with respect to the proposed Regulations;

Therefore, Her Excellency the Governor General in Council, on the recommendation of the Minister of Natural Resources and the Minister of Indian Affairs and Northern Development, pursuant to subsection 14(1)Footnote b of the Canada Oil and Gas Operations ActFootnote a, hereby makes the annexed Canada Oil and Gas Drilling and Production Regulations.

Interpretation

  •  (1) The following definitions apply in these Regulations.

    abandoned

    abandoned, in relation to a well, means a well or part of a well that has been permanently plugged. (abandonné)

    Act

    Act means the Canada Oil and Gas Operations Act. (Loi)

    artificial island

    artificial island means a humanly constructed island to provide a site for the exploration and drilling, or the production, storage, transportation, distribution, measurement, processing or handling, of oil or gas. (île artificielle)

    authorization

    authorization means an authorization issued by the Board under paragraph 5(1)(b) of the Act. (autorisation)

    barrier

    barrier means any fluid, plug or seal that prevents gas or oil or any other fluid from flowing unintentionally from a well or from a formation into another formation. (barrière)

    Board

    Board means the National Energy Board established by section 3 of the National Energy Board Act. (Office)

    casing liner

    casing liner means a casing that is suspended from a string of casing previously installed in a well and does not extend to the wellhead. (tubage partiel)

    commingled production

    commingled production means production of oil and gas from more than one pool or zone through a common well-bore or flow line without separate measurement of the production from each pool or zone. (production mélangée)

    completed

    completed, in relation to a well, means a well that is prepared for production or injection operations. (complété)

    completion interval

    completion interval means a section within a well that is prepared to permit the

    • (a) production of fluids from the well;

    • (b) observation of the performance of a reservoir; or

    • (c) injection of fluids into the well. (intervalle de complétion)

    conductor casing

    conductor casing means the casing that is installed in a well to facilitate drilling of the hole for the surface casing. (tubage initial)

    development plan

    development plan means the development plan that is approved by the Board in accordance with section 5.1 of the Act. (plan de mise en valeur)

    drilling program

    drilling program means the program for the drilling of one or more wells within a specified area and time using one or more drilling installations and includes any work or activity related to the program. (programme de forage)

    environmental protection plan

    environmental protection plan means the environmental protection plan submitted to the Board under section 6. (plan de protection de l’environnement)

    flow allocation procedure

    flow allocation procedure means the procedure to

    • (a) allocate total measured quantities of oil, gas and water produced from or injected into a pool or zone back to individual wells in a pool or zone where individual well production or injection is not measured separately; and

    • (b) allocate production to fields that are using a common storage or processing facility. (méthode de répartition du débit)

    flow calculation procedure

    flow calculation procedure means the procedure to be used to convert raw meter output to a measured quantity of oil, gas or water. (méthode de calcul du débit)

    flow system

    flow system means the flow meters, auxiliary equipment attached to the flow meters, fluid sampling devices, production test equipment, the master meter and meter prover used to measure and record the rate and volumes at which fluids are

    • (a) produced from or injected into a pool;

    • (b) used as a fuel;

    • (c) used for artificial lift; or

    • (d) flared or transferred from a production installation. (système d’écoulement)

    fluid

    fluid means gas, liquid or a combination of the two. (fluide)

    formation flow test

    formation flow test means an operation

    • (a) to induce the flow of formation fluids to the surface of a well to procure reservoir fluid samples and determine reservoir flow characteristics; or

    • (b) to inject fluids into a formation to evaluate injectivity. (essai d’écoulement de formation)

    incident

    incident means

    • (a) any event that causes

      • (i) a lost or restricted workday injury,

      • (ii) death,

      • (iii) fire or explosion,

      • (iv) a loss of containment of any fluid from a well,

      • (v) an imminent threat to the safety of a person, installation or support craft, or

      • (vi) pollution;

    • (b) any event that results in a missing person; or

    • (c) any event that causes

      • (i) the impairment of any structure, facility, equipment or system critical to the safety of persons, an installation or support craft, or

      • (ii) the impairment of any structure, facility, equipment or system critical to environmental protection. (incident)

    lost or restricted workday injury

    lost or restricted workday injury means an injury that prevents an employee from reporting for work or from effectively performing all the duties connected with the employee’s regular work on any day subsequent to the day on which the injury occurred whether or not that subsequent day is a working day for that employee. (blessure entraînant une perte de temps de travail)

    minor injury

    minor injury means an employment injury for which medical treatment or first aid is provided and excludes a lost or restricted workday injury. (blessure sans gravité)

    multi-pool well

    multi-pool well means a well that is completed in more than one pool. (puits à gisements multiples)

    natural environment

    natural environment means the physical and biological environment. (milieu naturel)

    near-miss

    near-miss means an event that would likely cause an event set out in paragraph (a) of the definition of incident, but does not due to particular circumstances. (quasi-incident )

    operator

    operator means a person that holds an operating licence under paragraph 5(1)(a) of the Act and an authorization. (exploitant)

    permafrost

    permafrost means the thermal condition of the ground when its temperature remains at or below 0°C for more than one year. (pergélisol)

    physical environmental conditions

    physical environmental conditions means the meteorological, oceanographic and related physical conditions, including ice conditions, that might affect a work or activity that is subject to an authorization. (conditions environnementales)

    pollution

    pollution means the introduction into the natural environment of any substance or form of energy outside the limits applicable to the activity that is subject to an authorization, including spills. (pollution)

    production control system

    production control system means the system provided to control the operation of, and monitor the status of, equipment for the production of oil and gas, and includes the installation and workover control system. (système de contrôle de la production)

    production project

    production project means an undertaking for the purpose of developing a production site on, or producing oil or gas from, a pool or field, and includes any work or activity related to the undertaking. (projet de production)

    proration test

    proration test means, in respect of a development well to which a development plan applies, a test conducted to measure the rates at which fluids are produced from the well for allocation purposes. (essai au prorata)

    recovery

    recovery means the recovery of oil and gas under reasonably foreseeable economic and operational conditions. (récupération)

    relief well

    relief well means a well drilled to assist in controlling a blow-out in an existing well. (puits de secours)

    rig release date

    rig release date means the date on which a rig last conducted well operations. (date de libération de l’appareil de forage)

    safety plan

    safety plan means the safety plan submitted to the Board under section 6. (plan de sécurité)

    seafloor

    seafloor means the surface of all that portion of land under the sea. (fond marin)

    slick line

    slick line means a single steel cable used to run tools in a well. (câble lisse)

    support craft

    support craft means a vessel, vehicle, aircraft, standby vessel or other craft used to provide transportation for or assistance to persons on the site where a work or activity is conducted. (véhicule de service)

    surface casing

    surface casing means the casing that is installed in a well to a sufficient depth, in a competent formation, to establish well control for the continuation of the drilling operations. (tubage de surface)

    suspended

    suspended, in relation to a well or part of a well, means a well or part of a well in which drilling or production operations have temporarily ceased. (suspension de l’exploitation)

    termination

    termination means the abandonment, completion or suspension of a well’s operations. (cessation)

    waste material

    waste material means any garbage, refuse, sewage or waste well fluids or any other useless material that is generated during drilling, well or production operations, including used or surplus drilling fluid and drill cuttings and produced water. (déchets)

    well approval

    well approval means the approval granted by the Board under section 13. (approbation relative à un puits)

    well-bore

    well-bore means the hole drilled by a bit in order to make a well. (trou de sonde)

    well control

    well control means the control of the movement of fluids into or from a well. (contrôle d’un puits)

    well operation

    well operation means the operation of drilling, completion, recompletion, intervention, re-entry, workover, suspension or abandonment of a well. (travaux relatifs à un puits)

    wire line

    wire line means a line that contains a conductor wire and that is used to run survey instruments or other tools in a well. (câble)

    workover

    workover means an operation on a completed well that requires removal of the Christmas tree or the tubing. (reconditionnement)

    zone

    zone means any stratum or any sequence of strata and includes, for the purposes of the definition commingled production, section 7, subsection 61(2), sections 64 to 66 and 73, subsection 82(2) and section 85, a zone that has been designated as such by the Board under section 4. (couche)

  • (2) In these Regulations, delineation well, development well and exploratory well have the same meaning as in subsection 101(1) of the Canada Petroleum Resources Act.

  • (3) In these Regulations, drilling installation, drilling rig, drilling unit, drill site, installation, production installation, production operation, production site and subsea production system have the same meaning as in subsection 2(1) of the Canada Oil and Gas Installations Regulations.

  • (4) The following definitions apply for the purposes of paragraph 5(4)(c) of the Act:

    production facility

    production facility means equipment for the production of oil or gas located at a production site, including separation, treating and processing facilities, equipment and facilities used in support of production operations, landing areas, heliports, storage areas or tanks and dependent personnel accommodations, but not including any associated platform, artificial island, subsea production system, drilling equipment or diving system. (matériel de production)

    production platform

    production platform means a production facility and any associated platform, artificial island, subsea production system, offshore loading system, drilling equipment, facilities related to marine activities and dependent diving system. (plate-forme de production)

  • (5) For the purpose of section 5.11 of the Act, installation means an onshore or offshore installation.

  • (6) For the purpose of section 58.2 of the Act, an onshore or offshore installation is prescribed as an installation.

PART 1Board’s Powers

Spacing

 The Board is authorized to make orders respecting the allocation of areas, including the determination of the size of spacing units and the well production rates for the purpose of drilling for or producing oil and gas and to exercise any powers and perform any duties that may be necessary for the management and control of oil or gas production.

 